LUBBOCK, TX (KCBD) - Construction is currently ongoing for the upcoming Buddy Holly Hall of Performing Arts and Sciences, which is scheduled to open in the spring of 2020.

It was only fitting the developers open up the construction site to media on Friday as Aug. 7 would have been the performers 82nd birthday.

To date developers have excavated more than 41,000 cubic yards of dirt, used around 3,400 tons of steel, more than 9,000 cubic yards of concrete have been poured and the concrete spiral inside of the venue will weigh 1 million pounds.

For the latest on Buddy Holly Hall click here: Buddy Holly Hall of Performing Arts and Sciences on schedule for 2020 opening